生产计划表-生产进度表分组机器号生产内容产品编号重要程度计划日期实际日期计划完成时间实际完成时间计划用时实际用时产线A组SDGJ1021组装手机SJH-241紧急2020/6/82020/6/82020/6/102020/6/1123产线A组SDGJ1022组装手机SJH-242日常计划2020/6/102020/6/102020/6/122020/6/1323产线A组SDGJ1023组装手机SJH-243紧急2020/6/122020/6/122020/6/182020/6/1563产线A组SDGJ1024组装手机SJH-244日常计划2020/6/142020/6/142020/6/212020/6/2278产线A组SDGJ1025组装手机SJH-245日常计划2020/6/162020/6/162020/6/202020/6/2145产线A组SDGJ1026组装手机SJH-246日常计划2020/6/182020/6/182020/6/232020/6/2355产线A组SDGJ1021组装手机SJH-241紧急2020/6/192020/6/202020/6/252020/6/2566产线A组SDGJ1022组装手机SJH-242日常计划2020/6/202020/6/202020/6/232020/6/2232产线A组SDGJ1023组装手机SJH-243紧急2020/6/222020/6/222020/6/252020/6/2533产线A组SDGJ1024组装手机SJH-244日常计划2020/6/242020/6/232020/6/282020/6/2945产线A组SDGJ1025组装手机SJH-245日常计划2020/6/262020/6/262020/6/272020/6/2913产线A组SDGJ1026组装手机SJH-246日常计划2020/6/282020/6/272020/6/302020/6/2921