项目计划进度表项目名称计划开始计划结束实际开始实际结束计划天数实际天数延期天数延期原因研发机械设计2021/6/12021/6/202021/6/12021/6/23353天设计延期研发电气设计2021/6/82021/6/142021/6/82021/6/16662天设计延期调试2021/7/12021/7/62021/7/12021/7/204514天人员问题装配2021/7/112021/7/162021/7/112021/7/1355打包货运2021/7/202021/7/212021/7/202021/7/23112天搬入2021/7/212021/7/282021/7/212021/7/2217电器现场调试2021/7/252021/8/12021/7/252021/8/5174天客户计划延期机械现场调试2021/7/302021/8/62021/7/302021/8/10174天调试延期验收2021/7/312021/8/72021/7/312021/8/12175天调试延期