建筑工程施工进度计划表序号分部分项工程名称工程量时间定额劳动量每天工作班数每班工作人数工作延续天数施工进度单位数量计划数采用数10/110/210/310/410/510/610/710/810/910/1010/1110/1210/1310/1410/1510/1610/1710/181基础工程人工挖土m33280.285 93.30 9412442混凝土垫层m369.11.789 123.60 12412163砖砌基础m384.10.678 57.02 5811544地圈梁施工m322.94.560 104.42 10411765基槽、房心回填土m33260.220 71.76 7211841架设塔吊、脚手架1一层主体结构砌砖墙m31661.120 185.52 186119102圈梁、构造柱、雨篷支模m282.70.080 6.61 71423现浇圈梁、构造柱、板、雨蓬等m327.94.560 127.32 12711684吊楼板、灌缝块2210.076 16.78 171545圈梁、构造柱、雨蓬拆模m282.70.026 2.15 21321二层主体结构砌砖墙m31661.120 185.52 186119102圈梁、构造柱,雨篷支模m282.70.080 6.61 71423现浇圈梁、构造柱、板、雨蓬等m327.94.560 127.32 12711684吊楼板、灌缝块2210.076 16.78 171545圈梁、构造柱、雨蓬拆模m282.70.026 2.15 21321三层主体结构砌砖墙m31661.120 185.52 186119102圈梁、构造柱、雨篷支模m282.70.080 6.61 71423现浇圈梁、构造柱、板、雨蓬等m327.94.560 127.32 12711684吊楼板、灌缝块2210.076 16.78 171545圈梁、构造柱、雨蓬拆模m282.70.026 2.15 21321四层主体结构砌砖墙m31661.120 185.52 186119102圈梁、构造柱、雨篷支模m282.70.080 6.61 71423现浇圈梁、构造柱、板、雨蓬等m327.94.560 127.32 12711684吊楼板、灌缝块2210.076 16.78 17154施工进度10/1910/2010/2110/2210/2310/2410/2510/2610/2710/2810/2910/3010/3111/1