365文库
登录
注册
2

顶管法施工方案(英文版)

275阅读 | 12收藏 | 4页 | 打印 | 举报 | 认领 | 下载提示 | 分享:
2
顶管法施工方案(英文版)第1页
顶管法施工方案(英文版)第2页
顶管法施工方案(英文版)第3页
顶管法施工方案(英文版)第4页
福利来袭,限时免费在线编辑
转Pdf
right
1/4
right
下载我编辑的
下载原始文档
收藏 收藏
搜索
下载二维码
App功能展示
海量免费资源 海量免费资源
文档在线修改 文档在线修改
图片转文字 图片转文字
限时免广告 限时免广告
多端同步存储 多端同步存储
格式轻松转换 格式轻松转换
用户头像
北风承欢南风未恋 上传于:2024-04-17
Method Statement for Pipe Jacking Construction of Pits The jacking pit with a dimension of 6mx5 clear opening with depth of 250mm below invert level of the steel pipe. The floor will be leveled by 100mm thick concrete blinding fixing tow I beams(1.5mx15cm) in the center of the pit for fixing jacking frame. Installation of Jacking Frame After the construction of drive, the jacking rig will be lowered into the pit and adjust to the control line and level. The rig will be used on this contract consist of two number of hydraulic cylinders with a capacity of 150 ton each to give a total jacking force of 300 tons. The rig will have guided rails, pushing plate and base plate to hydraulic power back with control unit. The hydraulic system will run through a diesel engine installed the top of the pit. The rig will installed to the correct line and level and check by the consultant in respect to level and alignment. Thrust Wall Constructing a concrete block behind the base plate of the rig to a dimension of 2x1.5x0.5m will be provided to take and distribute the jacking load. Pipe Jacking Operation A steel shield is used at the front of the pipe to accommodate the miner and to allow for steering of the pipe jack. The soil within the shield is manually excavated and loaded into a wheel skip for transport to the pit bottom. The miner does not dig outside the shield (both in front and radically) and the front, or cutting edge, of the shield is always kept buried in the face, so stability is maintained. The shield is thus used to trim the excavation to the size of the pipe thus minimizing the potential for settlement of the ground above the pipe jack. In the pit bottom, the skip is hoisted to the surface, emptied and returned to the used to loosen it prior to digging. The exact diameter of shield will be selected to suit the pushing pipes. As excavation continues, the shield is jacking forward using two hydraulic jacks thrusting from the back wall. When the shield is buried, the jacks are retracted and the first sleeve pipe lowered on to the rails. This in then pushed up to the shield and excavation can then continue. When the sleeve pipe is pushed home, the hydraulic jacks are retracted and the services (lighting& ventilation) disconnected. The next sleeve pipe is lowered on to the rails and the services reconnected and the cycle repeated until the shield is pushed into the receiving pit and the pipeline pushed into final position. Maintaining Line and Level In order to maintain the correct line and level, a graduated target plate is located within the shield. The site engineer notes the position of the visible sport on the target, this initial position is used as reference value to locate the relative position of the shield at all times during the drive. At each push, the site engineer monitors the position reference value with the help of level instrument and theodalite, thus giving a shield position (high or low, right or left) relative to the design position. Based on this information, the operator manipulates a correct course. Extending or retracting a combination of steering rams causing the front of the shield to articulate in the required direction carries out the steering. As the pipe follows the shield, the correct line and level will be maintained. At all times, the amount steering applied is kept to minimum. Fixing
tj